Organizing maintenance tasks is a specific and important field of pro-
ject and production management. Well-planned, properly scheduled and effectively
communicated maintenance tasks result in the accomplishment of more work that is
performed more efficiently at a lower cost. In maintenance and production manage-
ment, agile and lean approaches are becoming more frequently used, where preven-
tive/predictive maintenance (PPM) requires flexible project plans to decide which
system components should be maintained to achieve the target system reliability.
Maintenance projects have been treated as fixed sequences of corrective/preventive
tasks while the agile/lean approach allows and usually requires prioritizing tasks
and
reorganizing the project structure. The fixed structure of maintenance projects and
traditional maintenance project scheduling algorithms are not considered representa-
tive of these agile properties. The paper models the preventive resource-constrained
maintenance project scheduling problem and aims optimizing its maintainability. A
matrix-based algorithm is proposed to apply to both system and project structures
that
include both traditional and agile/lean project management approaches.